G3 Whittle Limited - 4th, 9th and 10th Floor
An Office refurbishment in the heart of Nottingham. The works comprised the stripping out of existing finishes and the refurbishment of two office suites fitted out to modern office standards.
Three Sixty established the scope of works, encapsulated within a schedule of works for all trades. Works were let on a trade by trade basis and all trades worked in accordance with the programme generated by Three Sixty.
Three Sixty, after successfully completing this project, repeated the procurement philosophy when undertaking the 1st and 2nd floors.